Activities on critical path Clause Samples

Activities on critical path. On request from the Employers Representative for work on critical path the Contractor must submit  Computerized programme twice a day.  However, should a logic change been executed by the Contractor, A revised network, bar-chart and time analysis must be submitted by the Contractor.  Key dates are considered as part completion dates and failure by the Contractor to meet those dated could result in the imposition of penalties by Eskom.  If any difficulties are foreseen in complying with the requirements of this document, these must be resolved with the Employers Representative before the tender is submitted.